EVM- Earning Value Method

  • Published on
    22-Oct-2014

  • View
    23

  • Download
    0

Transcript

EVM indicator

PV SV SPI

EV CV CPI

AC VAC TCPI

BAC

Deviation

Index

Forecast

EAC

Calculation

SV=EV-PV SPI=EV/PV

CV=EV-AC CPI=EV/AC

VAC-BAC-EAV TCPI-(BAC-EV) / (BAC-AC) EAC=BAC / CPI

( ) 4 3

PV EV AC BAC SV CV VAC SPI CPI TCPI EAC

Planned Value( Earned Value( Actual Cost( Schedule Variance( Cost Variance( ) )

) 3 ) ) ) ) ) ) ) EV ) 4 1

Budget at Completion(

Variance at Completion( Schedule Performance Index( Cost Performance Index( To-Complete Performance Index( Estimate at completion(

SV > 0

SPI > 1

EV

CV > 0

CPI > 1

EAC

TCP

PV SV 0

EV CV SPI

AC

BAC VAC CPI TCPI

1

PV SV SV = 0 SPI SPI = 1 SPI < 1 SV < 0

AC CV CV = 0 CPI CPI = 1 CPI < 1 CV < 0

VAC

Recommended

View more >