EVM- Earning Value Method

  • Published on
    22-Oct-2014

  • View
    23

  • Download
    0

Transcript

EVM indicatorPV SV SPIEV CV CPIAC VAC TCPIBACDeviationIndexForecastEACCalculationSV=EV-PV SPI=EV/PVCV=EV-AC CPI=EV/ACVAC-BAC-EAV TCPI-(BAC-EV) / (BAC-AC) EAC=BAC / CPI( ) 4 3PV EV AC BAC SV CV VAC SPI CPI TCPI EACPlanned Value( Earned Value( Actual Cost( Schedule Variance( Cost Variance( ) )) 3 ) ) ) ) ) ) ) EV ) 4 1Budget at Completion(Variance at Completion( Schedule Performance Index( Cost Performance Index( To-Complete Performance Index( Estimate at completion(SV > 0SPI > 1EVCV > 0CPI > 1EACTCPPV SV 0EV CV SPIACBAC VAC CPI TCPI1PV SV SV = 0 SPI SPI = 1 SPI < 1 SV < 0AC CV CV = 0 CPI CPI = 1 CPI < 1 CV < 0VAC

Recommended

View more >